Construction Update

What has already happened:
- Removal of 10,000 gallon fuel oil storage tank in front of Andrews Hall.
- Wood sidewalk constructed behind Andrews Hall.
- Constructed temporary office for Dr. Willingham.
- Jackhammered and removed existing kitchen floor slab.
- Completed selective separation of old Nursery area from existing building.
- Started layout of two new bathroom areas inside Andrews Hall.
- Completed exterior demolition on east side of Andrews Hall in new Ground Floor and First Floor bathroom areas, started layout and mechanical/electrical rough-ins.
- Completed removal of Silas Andrews marble plaque and cross at entrance and placed in storage.
- Completed all asbestos abatement work in old nursery rooms, bathrooms, and at exterior soffits.
- Construction barricades for dust and sound installed throughout interior of Andrews Hall. Masonite surfacing has been added for smoother texture.
- 1940 cornerstone has been removed and will be re-installed later.
- The ramp for the Mechanics Street entrance to Andrews Hall is finished. This is now the only entrance from that side of the building.
- Tree removal is finished for now. A few other trees will be removed later.
- Completion of emergency exit from top floor of Andrews Hall.
- Nursery has moved to Andrews Hall, Room 104 (AH-104).
What will happen next:
- Complete utility pipe tunnel in kitchen/Fellowship Hall area.
- Continue excavation for building additions along Mechanics and Church Streets.
- Continue with re-construction of new bathroom facilities inside Andrews Hall.
- Start plumbing and electrical rough-ins in both new bathrooms.
Questions?
- Speak with any staff member or pastor or call the church office. We want to keep you fully informed as we move through this exciting venture!